Exercise condition:

5
A publisher recruited 9 persons to proofread the books in 22 days which contains a total of 2000 pages. If he recruited again 4 persons to accelerate the project, then in how many days they will complete the work.
 
  
The project will be completed in  days.
 [Note: Insert the answer as a whole number].