An engineer estimates that 25 persons will finish a construction project in 45 days, but the owner informed him to finish the work in 27 days, then how many persons will the engineer require to finish the job in time.
 
  
The engineer requirespersons to finish the project in 27 days.
[Note: Insert the answer as a whole number].