In a company, Sam takes 12 days to complete a piece of work, and Mohan takes 16 days to complete a piece of work. Together they work for \(₹\)4800. When Akhil joined them, the work was completed in 6 days. What was the amount paid to Akhil?

The amount paid to Akhil is \(₹\).
Answer variants:
602
600
601
599