In a company, Vimal takes 16 days to complete a piece of work, and Kishore takes 20 days to complete a piece of work. Together they work for \(₹\)2400. When Saran joined them, the work was completed in 4 days. What was the amount paid to Saran?
 
shutterstock_723029344.jpg
 
The amount paid to Saran is \(₹\)
.
Answer variants:
239
241
240
242